Sabah Shell Petroleum Company,
Malaysia, required the full refurbishment of three gas compressor
packages removed from their St. Joseph platform. On completion of
the refurbishment they were to be reinstalled on the South Furious
and Barton Platforms.
In a joint partnership with our local representative in Malaysia,
Petra Resources Sdn Bhd, a project team was formed to undertake the
work.
The scope of this project was significant and covered the complete
refurbishment of the 3 packages including; Dresser Rand compressor
overhaul, Caterpillar engine overhaul, Lufkin gearbox inspections,
Holset coupling inspection and overhaul, Air Exchanger testing and
re-certification, fan replacement and repair, full vessel testing
and weld repair of damaged vessels, valve and actuator repair and
replacement, structural reinstatement of man ways and scaffolding.
AMOT upgraded the existing AMOT pneumatic control system and sensors,
with an electronic PLC based control panel for Zone 2 installation
including electronic sensors. AMOT Engineers provided on site supervision
for the installation of all instrumentation and were fully responsible
for offshore commissioning of the compressor units.